|  In January of 2012, the city learned that they had won a $675,000 
			grant through the Illinois Department of Commerce and Economic 
			Opportunity. The CDAP Flexible Opportunity grant was given to the 
			city with stipulations that the money be used for three purposes: 
			Develop an overall downtown revitalization plan, fund building 
			demolition and code compliance work within the downtown area, and 
			fund facade improvements that are historically accurate and 
			aesthetically pleasing. The grant also came with a local match stipulation, and the city 
			of Lincoln was required to add $100,000 to the grant for a total of 
			$775,000 to be spent. The city appointed a steering committee to move forward with 
			accomplishing these goals, with a deadline of December 2013 for all 
			the work to be done and all the funds spent. Tuesday evening, Doolin told the council that in realizing the 
			funding could not all be spent by the deadline, the committee had 
			requested and received an extension from DCEO. The city now has 
			until Sept. 30, 2014, to use all the grant funding or the money not 
			used will have to be given back to the state. 
			 Doolin offered a recap of how the grant money has been used to 
			date. The first portion of the grant requirement was to develop a 
			plan for revitalization. Doolin said that plan has been completed at 
			a cost of approximately $388,000. He said the work done with these 
			dollars included many studies performed by experts in specific 
			fields such as parking studies, traffic studies, historic 
			preservation studies, broadband infrastructure studies and much 
			more, as well as developing a written plan using the information 
			gathered. Doolin said what is left of the grant plus city match is 
			approximately $386,000. He explained that one component of the grant was to use a large 
			portion of the funding for demolition of properties in the downtown 
			area. Doolin expressed that this was somewhat of a challenge because 
			fortunately, the city does not have many buildings in the downtown 
			area that warrant demolition. However, they did find one. Doolin said the committee was recommending that approximately 
			$40,000 be spent to demolish the building at 217 S. Sangamon St. The 
			cost would be divided, with the grant paying $36,000 and the city 
			providing $4,000. The property in question has been a troubled property in the city 
			for several years. Located next door to the old Alexander Lumber 
			building, an exterior wall of the building began to crumble in 
			December of 2008, and over a several-hour period, much of the wall 
			went tumbling down near the parking lot of Alexander's. The building had been empty for some time prior to that, and in 
			the opinion of the city zoning officer at that time, Les Last, was 
			uninhabitable. The building was consequently condemned. The property 
			owner, Mark Gates, took no action to demolish or refurbish the 
			building, and there was not enough money within the city coffers to 
			do anything about the large, crumbling structure. Tuesday night, Doolin said the grant funds would carry the lion's 
			chare of the cost, and the city would be able to do away with one 
			more problem property in the city. To do this, the city could put 
			the property in the fast-track demolition program, and within 60 to 
			90 days of approval from the council, the building could come down. Doolin stressed that this would help the city and also fulfill 
			the grant requirement, and thus the committee was recommending that 
			the council approve the demolition. Next, Doolin said the committee was ready to recommend that one 
			block of the downtown square be redesigned, based on a streetscape 
			plan put together by the committee. The committee would like to do a 
			complete design upgrade of the 500 block of Pulaski Street. 
			
			 In addition, they want to do a wraparound on each end of the 
			block, taking the new streetscape just past the old Oasis building 
			on the west side, and just past Bock Realtors on the east side. This 
			would also include work on both sides of the intersections. The plan 
			includes building the sidewalk area out into the intersection so 
			that pedestrians can prepare to cross traffic without actually being 
			in the line of traffic as they are now. Doolin told the council that one big advantage to doing this 
			block was that it would provide a "living model" of what the city 
			hopes to accomplish for the entire downtown area. He said doing so 
			would help increase public support of the downtown projects and 
			would also be beneficial in obtaining future grants. He said the city has missed out on a few grants because they 
			don't have a project physically started, so getting one block 
			underway would improve the odds of getting grant funding for other 
			streetscapes in the future. Doolin also explained why Pulaski Street was chosen as the 
			starting point. He said the sidewalks along that area are in bad 
			shape and in need of replacement. He also said that in the downtown 
			area, that block does not have the elevation changes that some of 
			the others do. In other words, the sidewalk is closer to street 
			level. In addition, that part of the downtown area experiences 
			strong sewer odors that infiltrate the area businesses. Part of the 
			plan would include sewer work to remedy this. He also told the council that when the committee submitted this 
			street to DCEO for their required approval, it was one the state 
			agency really liked as the first project because of the Oasis and 
			the Arcade, which both generated a lot of foot traffic in the city. Finally, Doolin said the source for lighting throughout the 
			downtown area was in that region, which would make it easier for the 
			tie-ins the project would require. 
			[to top of second column] | 
 
				 Bruce Carmitchel asked about the Oasis. DCEO had approved the 
				project before the Oasis fire. Carmitchel wondered if the state 
				would still support this as the first project with the Oasis 
				gone. Doolin said the state had not been informed that the Oasis 
				was gone, but at this point he didn't feel like that would 
				matter to DCEO. He noted that now that it has been approved, 
				making a change with DCEO would be very difficult. Doolin said that with the city's approval, the two recommended 
			projects, demolition of 217 S. Sangamon and a new streetscape for 
			Pulaski Street, both could be completed by the DCEO deadline. He 
			stressed that if for no other reason, it was very important that the 
			city use the money in the grant, and this would do that. However, the drawback to the plan is that it will not only use 
			the approximately $386,000 remaining, it will also require an 
			additional $200,000 that is not currently in the city's budget. Doolin said he realized this was all very complicated, but the 
			bottom line is, to complete the streetscape plan, there are 
			components that the DCEO grant will not pay for. The grant will pay 
			nothing for engineering costs associated with the design. It will 
			not pay for street lighting, and it will not pay for the decorative 
			components such as benches, trees or planters. Doolin said the city would have to find $57,000 to pay the 
			engineering costs and another $148,000 to pay for the non-funded 
			components of the plan. He recapped that those components would be 
			lighting, light posts, the sewer repair, trees, planters and 
			benches. Doolin talked about the logic of this, saying that in order to do 
			the new sidewalks, the existing lighting would have to come out, and 
			then be put back in. DCEO will not pay for that. He said the 
			committee believes it would be silly to start the project and not 
			finish it completely. He also told the council one of the big drawbacks in the cost is 
			the fact that it is only one block. He said construction costs are 
			higher on small projects. He noted that if the city had the money to 
			do several blocks at a time, which they don't, the overall cost of 
			construction would be less. 
			
			 During discussion, the question came up as to what was included 
			in the lighting portion. Doolin said it was street lighting and 
			lighting at intersections; it did not include traffic control 
			devices. It was also questioned whether the city had to commit to doing 
			the sections right off Pulaski on South Kickapoo and McLean streets. 
			Doolin said they did not.  The committee was making the recommendation for the side streets 
			in order to fully use all the grant money. He said the committee was 
			going to recommend that the city approve the "whole pie," but that 
			if the costs got out of hand, they could revisit the plan and do 
			away with the work on the two side streets. Doolin said the committee's official recommendation was that the 
			city commit to spending all the grant funds, $302,000; spending the 
			balance of its required match, $79,500; then spend the additional 
			$57,000 for engineering; and finally, commit to another $148,000 to 
			complete the decorative and lighting component of the plan. Doolin told the council that the committee needs the city's 
			commitment so it can move forward with the plan. He added that if 
			the city wants to look at a different block, that would cause delays 
			in the process and probably cause the city to lose the balance of 
			the grant. Doolin also told the council the dollars that were needed 
			immediately would be the $57,000 for engineering. The $148,000 would 
			be needed later.  Melody Anderson asked if there had been any conversation as to 
			where the $148,000 would come from. Marty Neitzel, who is on the 
			steering committee with Doolin and Lanterman, said the discussion 
			had included taking the money from the capital improvement funds. It should be noted that in implementing the utility tax for the 
			city of Lincoln, Mayor Keith Snyder's original plan called for 
			dollars for downtown revitalization. The plan included issuing a $2 
			million bond with annual payments of $250,000, all paid by utility 
			tax collections. Kathy Horn wondered if CEDS could help with funding for a project 
			like this. Doolin said that was a possibility and that an 
			application could be submitted through them. It was also discussed that the city has applied for a $2 million 
			grant through the Illinois Transportation Enhancement Program. 
			Darren Forgy of Prairie Engineers and also a member of the steering 
			committee said the ITEP grant application would cover streetscape 
			work on 10 downtown blocks associated with Broadway Street. He noted 
			that in that grant the city's match would be $500,000. 
			
			 Bruce Carmitchel asked if area businesses would have to bear any 
			costs in this project. Doolin said where they might have to 
			contribute would be in creating ADA-compliant entryways into their 
			own businesses. The city is required to make the sidewalks 
			accessible, but the building owners are responsible for making their 
			entries accessible. As the discussion began to wind down, Snyder asked if the 
			committee's recommendations could be placed on next week's agenda. 
			Neitzel said yes, to put it on. She also noted that if the council 
			is not ready to vote come Monday, it can be tabled to a future 
			meeting. 
            [By NILA SMITH] |