|  However, he also delivered a stunning blow when he told the council 
			that the projected costs of the project far exceed the original 
			estimate. In the city's capital improvement plan, the cost of the 
			project was estimated to be $1 million. Tuesday night Forgy said the 
			cost estimate now sits at $1.5 million. The original plan for Pulaski Street includes reconstruction of 
			the five blocks between Hamilton Street and Ladue Street.  The work would include reclaiming of the original bricks that are 
			now hidden under layers of asphalt. The purpose of pulling up all 
			that brick is so that it may be used later to refurbish existing 
			brick streets in the city. In addition, the project calls for redoing the sewer lines in 
			that five-block area. This was discussed as part of the five-year 
			plan. Lincoln's sewage system in many areas still uses lines laid in 
			the 1800s. It is also what is classified as a combined sewer, which 
			means raw sewage and stormwater runoff travel in the same pipes to 
			the waste treatment plant, something that is highly frowned upon by 
			the Illinois Environmental Protection Agency today. 
			 In discussing the long-term plans for the city, Forgy had 
			mentioned that as streets are repaired and improved, the city would 
			be well advised to go ahead and redo the sewers at the same time. 
			Eventually, the EPA is going to require that raw sewage and 
			stormwater travel to the waste treatment plant in separate lines. 
			Forgy said that doing the work when streets are being repaired would 
			save the city having to tear out good roads later for the sake of 
			sewer replacement. Tuesday night, Forgy said much of the increase in costs was due 
			to the sewer work in the project. He also told the council that the figures he is giving them now 
			are based on a state average of what the project should cost, and 
			there are no guarantees that the bids will come in at that price. He 
			said he's seen times when bids would come in much lower than the 
			estimate, but again he couldn't promise that either. During discussion, Melody Anderson asked what effect this big 
			cost change would have on other projects slated to be completed this 
			year. City administrator Sue McLaughlin said that at the moment there 
			is not an answer to that question. She said there had been some 
			brainstorming on how to deal with this, but at the moment she and 
			the city engineer do not have a definite plan. 
			
			 Forgy did mention that one option they had discussed was to 
			reduce the project from five blocks to four. He said that if the 
			city chose to do that, the block in front of the Lincoln IGA is the 
			one in the best condition at the moment, so it could perhaps be 
			eliminated from the project. Anderson asked if that was a decision the council could make 
			after the bids were received, and Forgy said it was. 
			[to top of second column] | 
 
			 Forgy then asked if he could go ahead and advertise for bidders 
			on the project. While the council in the past has voted in order to 
			approve going out for bids, it is not actually required. It was 
			agreed that if the general consensus of the council was to go 
			forward, Forgy could get the ad for bidders placed right away. The 
			council did consent. Forgy also said that letters need to be sent out to property 
			owners along the street, explaining what would be happening and 
			inviting anyone with concerns to contact the city engineer. He said 
			he could send those letters out now while the city awaits the bids. Jeff Hoinacki asked how long it would take to get the bids back 
			and was told it would be a two-week process. Ads will be placed 
			immediately, with bid packets due back in two weeks, which would be 
			the first full week in August. Bids could be announced at the Aug. 
			13 committee of the whole workshop and voted on at the Aug. 19 
			voting session. In other street concerns, Forgy said he had contacted the low 
			bidder of the Oglesby bridge demolition project and inquired why the 
			bid had come in significantly higher than anticipated. The 
			contractor had responded with two reasons. He said first the city 
			was not providing a dump site for the materials to be hauled away. 
			The contractor will have to haul the debris away at his expense. 
			Secondly, he told Forgy that he had based his labor costs on the 
			prevailing wage laws, and he felt that what he was bidding was a 
			fair price. Forgy said he had also contacted a few contractors who did not 
			bid on the project and asked them why. He was told that the project 
			was too small. 
			
			 Forgy said he had talked to the council previously about 
			combining the Oglesby project with something else, such as the 
			Pulaski Street project, but now he was on the fence, not sure it 
			would make that much difference in the price. Forgy was asked if the Oglesby project could be added to the 
			Pulaski bid packet as an "alternate," and he said it could. 
			McLaughlin said she felt the city should do that as she felt it 
			would be worth finding out if they could save some money. Forgy was then asked if adding Oglesby to the bid specifications 
			would delay the process. Forgy said it would take a couple of extra 
			days to amend the bid packets, but he didn't believe it would delay 
			the process as a whole. In the end it was decided that the bid specifications for the 
			Pulaski Street project will include Oglesby as an alternate. The 
			council will then decide if they want to keep the two projects 
			separate or combine them, based on the cost of the bids. 
			[By NILA SMITH] |