|  Demolition of the existing pool and construction of the proposed new 
			facility were scheduled to begin in late August. However, the bid 
			response was very light. A number of parameters outside of both the 
			park district's and design team's control resulted in public bidding 
			at a very inopportune time. The few bids received exceeded the 
			engineer's opinion of probable construction costs by a sizable 
			amount. The Board of Commissioners unanimously rejected all bids. 
			
			 Although disappointing, the bid results have not discouraged the 
			park district from moving this project forward. Every available 
			option for reducing costs without compromising the design is being 
			explored. Additional funding sources are being sought as well.  
			[to top of second column] | 
 
			 The project is scheduled to be rebid in early January of 2014. 
			Construction is set to begin in March, providing contractors with a 
			longer and more favorable timeline for completion prior to the 2015 
			season.  A news release from the park district commented: "We are 
			confident the January bidding will provide a more competitive 
			environment for the project. We appreciate the public's 
			understanding as we overcome the challenges with patience and 
			perseverance." 
			[Text from file received from