|  The city has been plagued with issues regarding this project, many 
			of them due to the lack of sufficient funds to actually repair or 
			replace the bridge. The saga began in February 2011 when then-city 
			engineer Mark Mathon reported to the city that the bridge was no 
			longer safe for vehicle traffic. The bridge was immediately closed, 
			and aldermen began discussing its future. Replacement of the bridge 
			was estimated then to cost well over $250,000 -- money the city 
			didn't have in its budget. As time progressed, discussion turned to looking at alternatives 
			to replacing the bridge. Melody Anderson, who lives on Oglesby, 
			noted that in the neighborhood, there didn't seem to be a great deal 
			of concern over the fact that the bridge was closed. Aldermen then began discussing whether the bridge should be 
			replaced or should just be demolished. In the end they made the 
			decision to demolish it and save the money that might have been 
			spent on replacement for the time when one of the other bridges 
			crossing Brainard's Branch might need attention. 
			 In those discussions it was noted that the bridges on Jefferson, 
			Grand, Palmer and Union were all of similar construction and age. Of 
			those four, aldermen considered that Jefferson, Palmer and Union 
			were all more traveled than Oglesby and would cause a problem for 
			the related neighborhoods if they would have to be closed. Discussions that continued for the next several months addressed 
			questions such as whether the bridge could be saved for walking 
			traffic, if it should be taken out, and if so, how the new dead ends 
			should be finished, if there a need for cul-de-sacs, and more. In the meantime, the bridge was continuing to deteriorate. This 
			year city engineer Darren Forgy told the council he didn't feel the 
			bridge would be safe for foot traffic. Even as recently as last 
			week, he told the council that with some dollars invested, the 
			bridge could be made safe, but it would be only a temporary fix. He 
			estimated that within the next couple of years the bridge would be a 
			hazard to any type of traffic. Earlier this year the city went out for bids for a demolition 
			project that would include removing the bridge and doing some finish 
			work at the dead ends. The proposal at that time included doing some 
			curb work and installing permanent barriers to keep vehicles from 
			accidentally driving into the drainage ditch. There were also plans 
			to include some type of decorative element, such as landscaping or 
			planters, to make the area more attractive for Oglesby Avenue 
			residents. Included in that plan, the city would hire contractors for the 
			demolition, and city street crews would be used to do much of the 
			finish work. 
			[to top of second column] | 
			 
			But, when the bids came back, the cost of demolition was much more 
			than expected. The bids were rejected, and the city attempted to 
			combine the Oglesby project with another, larger project: Pulaski 
			Street. But they got no takers on that. Two weeks ago, Stark Excavating was awarded the bid for the 
			Pulaski Street project, and last week Forgy reported that he had 
			talked to Stark about taking on Oglesby as well. Forgy said he began by asking Stark to match the original low bid 
			of $35,000 for the Oglesby work, but Stark said he couldn't do that. 
			The lowest he would be able to go was $38,250. Forgy said one of the big issues driving the cost up was the fact 
			that the city had no place close by where the debris from the bridge 
			could be hauled. Stark had told Forgy that if the city could provide 
			such a place within 4 miles of the bridge, he would lower the price, 
			but that wasn't possible. Last week the council discussed postponing the project once 
			again, but Marty Neitzel pointed out that with each delay, the cost 
			gets higher. She quipped that by next year, the same bid could cost 
			$70,000, and Anderson agreed. According to Sue McLaughlin, city administrator, the city can 
			stretch the budget to cover the demolition cost, but there won't be 
			money this year to do the finish work. The council decided to move forward with the demolition, put up 
			temporary barriers at the dead end and try to incorporate the finish 
			work into next year's budget. The council has had to deal with problems of bids and costs 
			coming in too high on several projects. The Pulaski Street project 
			came in with a bid cost of $1.7 million and an estimated final cost 
			of $2.1 million, considerably higher than expected. 
			 Aldermen have expressed that they are determined to get at least 
			some of these projects started, if not completed, this year, and 
			McLaughlin has told them it is possible, but it will stifle cash 
			flow in the infrastructure budget, and somewhere down the road, 
			other projects may have to be postponed until more money is 
			available. In the meantime, demolition of the Oglesby bridge will begin 
			early next month, and the Pulaski Street project will begin yet this 
			fall, with expectations that at least one block will be finished 
			before cold weather sets in. 
            [By NILA SMITH] |